plaintiff: [] defendant: - CHINA LIGHT & POWER COMPANY LIMITED jurisdiction_code: null jurisdiction_name: null case_location: - 香港特別行政區 case_reason: >- Applicant, Chow Chi Keung, claims compensation from respondent, China Light & Power Company Limited, case_object: - compensation for diminution in value of property judgment_result: - charge: Diminution of value due to wayleave (liability issue) result: Allowed. The court found that while the transmission lines cross only two-thirds of the property, their presence affects the entire property and significantly detracts from its appearance and enjoyment. - charge: Quantification of compensation (quantum issue) result: Partially allowed. The court determined a lump sum compensation of HK$20,000 for the diminution in value of the applicant's property and awarded interest since March 30, 1981. judgment_summary: >- In this case, Chow Chi Keung, a registered Crown lessee, sued China Light & Power Company Limited for compensation due to the construction of a 400 KV transmission network affecting his property's value. The core issues were whether the company was liable and how much compensation should be awarded. involved_entities: - entity_name: His Honour Judge Cruden reason: Presiding Officer in this case, responsible for fact-finding and adjudication. - entity_name: M.W. Phillips, Esq. reason: Member of the Tribunal, involved in the decision-making process. - entity_name: China Light & Power Company Limited reason: Respondent in the case, responsible for constructing the 400 KV transmission network. - entity_name: Chow Chi Keung reason: Applicant in the case, registered Crown lessee of the land affected by the construction.